Chicken or Egg, Part 2 – Webinar Summary 

At the first meeting in the "Chicken or Egg?" series, we talked with Konrad about where to start changing planning: with the process, with the system, or with both at once. The conclusion was: decisions first, then the process - and the system should support them, not replace them. In the second part, on November 19, we tipped the scales towards technology. Instead of slides, Artur Bula and Oskar Skrzyniarz showed the system - live, on data from a fictional but very realistic company.

At the first meeting in the “Chicken or Egg?” series, we talked with Konrad about where to start changing planning: with the process, with the system, or with both at once. The conclusion was: decisions first, then the process – and the system should support them, not replace them. In the second part, on November 19, we tipped the scales towards technology. Instead of slides, Artur Bula and Oskar Skrzyniarz showed the system – live, on data from a fictional but very realistic company. 

For our testing ground we chose DemoMet sp. z o.o., a manufacturer of steel enclosures: control cabinets, wall-mounted enclosures and operator consoles. Every product goes through the same five steps – cutting and bending, welding, painting, assembly, and inspection and packing. Simple? On paper, yes. In the plan – not necessarily. 

We made one thing clear: this was not a sales presentation. We wanted to show what technology can do today and ask you what you expect from it. 

Here are the main takeaways from the meeting: 

Buckets or bars? 

We usually see the plan for the next 16 weeks the way we would in Excel: columns, weeks, how much and when. These are our “buckets”. The schedule for the next 4 weeks is already “bars”, i.e. a specific order, on a specific work center, from this second to that one. When moving from one world to the other, everything usually changes at once: buckets into bars, aggregate capacities into specific resources, product groups into individual items. 

In the demo we adopted a simplification that is a topic for discussion in itself: we calculate the medium-term plan and the schedule on the same data – the same items, BOM structures and routings. Only the time bucket changes. Is that how it should be? Or is it better to plan the medium term on aggregates? We would be happy to show such a variant at the next meeting. 

Why do we need MRP? 

Artur promised to keep asking this question until someone convincingly tells him that it makes no sense. Classic MRP is 1960s logic: an availability table, opening stock, demand, negatives to eliminate. Then CRP separately, and then materials and capacities again. And round and round. 

In the demo we went through three scenarios: 

  1. An unconstrained plan for finished goods only. 
  1. An unconstrained plan at all BOM levels – materials and capacities in a single run. 
  1. A constrained plan with a short-term “wall”. 

The very first calculation revealed overloads: the paint shop at 153% in one of the weeks, electrical assembly even higher. Importantly: we calculate capacity utilization based on the same data the schedule uses. No theorizing along the lines of: “we’ll make 10,000 units of this product per week”. 

The wall the plan bounces off 

The most interesting moment of the first part of the demo: the constrained plan. The algorithm received the entire demand and a single task: move the tall towers of overload towards the present and spread them out as well as possible. Just don’t drive into the short term, because there’s a wall there. 

The result? It’s plain to see that in electrical assembly – no matter what we did – the plan won’t close. 366% capacity utilization. And that is exactly the information a planner needs a few weeks in advance, not on the day of execution. The system also shows which orders and which customer orders are behind the overload. 

What next? That’s the company’s decision. A phone call to the customer, a subcontractor, extra people in assembly, temporary work. We change the assumptions, calculate another version and compare. 

And where does this plan come from? From a heuristic algorithm – in this case a genetic one. It is not an LLM. It works according to a multi-factor objective function and calculates for as long as we let it. More time usually means a better result. 

Where does the plan end and the schedule begin? 

The boundary between the medium and short term is not just a line on the timeline. We asked you a few questions that in many companies still remain open: 

  • Is it a straight line at the end of the week, or a “dashed” boundary – shorter for assembly, longer for a process that requires shipping to a subcontractor? 
  • Who authorizes the orders passed to the schedule, and on what basis? 
  • What feedback should the schedule return to the medium-term plan: what didn’t fit, what was moved, what the real times are? 
  • Does the plan simply roll forward, with the overload towers shifted to the right? 

Our proposal for handover conditions is simple: the plan must be feasible (capacities and materials checked), the boundary clearly defined, orders authorized, and the data the same on both sides. 

Backward, forward and the conversation with the board 

In the next version of the plan, we calculated the medium term backward from the wall, and the short term forward, so that work would start immediately. The Gantt chart then shows the production sequence, and orders with problems light up in red. 

Then came the scenario the sales department likes best: “do everything”. Optimization from today, forward, without exceeding available capacity. No red fields, work centers loaded at almost 100%, but quite a few orders land in the late-orders basket. 

And here the topic of versions comes back. Every saved version of the plan – in a database, not in Excel – is an argument in the conversation with the board: “We talked about this eight months ago, we did nothing about it, now we’re feeling the consequences”. Instead of 16 MRP and CRP runs, the planner can prepare several versions with different demand, availability and rules, and then simply compare them. 

The paint shop is down. Now what? 

A classic: one of the paint booths is switched off. A simple click in the work center calendar, a new optimization, and an answer to the question “what happens if…”. The system didn’t overload the paint shop, but the number of late orders rose from just over 50 to 114. 

The second scenario is a rush order from a customer. The sales manager calls: “I’ve got a customer on the line, when can you do this?”. The new order goes into a separate basket, and the system looks for the earliest possible date within its own “microworld”. It doesn’t recalculate the whole plan and doesn’t violate the frozen zone – you can freeze a department, a period or individual orders. 

Technology makes this possible. The question is whether such a process of promising delivery dates exists in your company at all. 

LLM: suggests or decides? 

Finally, an assistant based on a large language model. Here we set out a clear division of roles: 

  • The algorithm and optimizer calculate. The constrained plan, the schedule – searching for the best solution within a given time. 
  • The LLM suggests. It answers questions, explains the result, proposes changes and launches the tools that do the calculating. 
  • The planner decides. The LLM can read data on its own, but it can change the plan only through tools and with human approval. 

So let’s not waste tokens on repetitive and deterministic tasks. The greatest value appears where the assistant suggests something non-obvious. For example: “don’t move this order – in the last 18 versions, customers cancelled such orders anyway”. 

For that to happen, the assistant needs data: master data (items, BOMs, routings, calendars), the state of the plan and its versions, rules written in words, the history of the planner’s decisions, and execution data. Plus a company glossary – because what does “urgent” actually mean at your company? – and permissions: the LLM sees only what the planner sees. 

To be honest: conversation, analyses, summaries and basic actions already work today. Translating business rules written in words into algorithm functions, analyzing plan versions and a company knowledge base are under construction. 

Integration instead of another island 

As a side note, though for us it is fundamental: a planning system cannot be yet another island. Order proposals go to the ERP, and data should flow in from ERP, MES or SCADA. And when we find a key Excel file in the company? We pull its data into the system so that it is organized and available for analysis – including for AI. 

Chicken or egg? Let’s act in parallel 

If we had to sum up the second part in three sentences, they would be: 

  • Decisions: the system calculates scenarios, the human chooses and is accountable. 
  • Process: medium-term plan, schedule, execution – with versions and a freeze window. 
  • System: in small spoonfuls. One department, one line, quick results. 

Technology can be the impulse for real transformation, but only if, together with it, we change the process and the way people work. Simply implementing a ready-made tool is not yet a transformation. 

What’s next? 

We have quite a few scenarios left over from the demo – especially those in which the AI assistant performs actions in the plan by itself. We’ll show them at the next meeting. We are also planning a workshop together with Konrad: more time, more “why did it calculate this way?” questions. 

We promised participants a material with a list of the data worth preparing before you start thinking about planning with optimization. In it, we will also describe the steps of such a project and the systems we can integrate with. 

Thank you all for taking part, for the questions in the chat and the answers in the surveys! 

Or perhaps you’d like to test it on your own data? We are looking for companies for joint testing of the LLM assistant. Write to us or book a call – we love talking about planning.